Cooling Plant Al Reem Island







- Water & Wastewater
Cooling Plant Al Reem Island
Cylingas is a fabrication company based in Dubai and was established back in 1974, they fabricated the TES tanks used on the Shams District Cooling Plant. The plant is being built for Tamouh Investments for their Reem Island Communities.
Foam Insulation along with a polymer coating solution is becoming a more accepted way of insulating TES tanks as the system provides both insulation and a flexible seamless waterproofing membrane.
VIPSHIELD was chosen by the client as it provided extended warranties and a maintenance free solution.
Application steps:
1) Surface repair & preparation
2) Application of Spray Foam
3) Application of 2mm QuickSeal PP350 - hot spray applied polyurea
4) Application of one coat of QuickCoat PU Topcoat
VIPSHIELD was chosen by the client as it provided extended warranties and a maintenance free solution.
Application steps:
1) Surface repair & preparation
2) Application of Spray Foam
3) Application of 2mm QuickSeal PP350 - hot spray applied polyurea
4) Application of one coat of QuickCoat PU Topcoat
Reference details
Project description
Cooling Plant Al Reem Island
City
Abu Dhabi
Country
United Arab Emirates
Size (in m²)
13000 m²
Year
2021
Customer
Cylingas Company LLC
Applicator
Petrichor LLC
Used products
QuickSeal PP350
QuickSeal PP350 is a spray applied, instant curing flexible membrane that can be built to any thickness in one application.